Please let me know if you need any further assistance.
2.1. : * Sort the jobs in arrival order. * Schedule each job on the first available machine. Please let me know if you need any further assistance
| Job | Start Time | Completion Time | Lateness | | --- | --- | --- | --- | | 3 | 0 | 1 | 0 | | 1 | 1 | 4 | 0 | | 4 | 4 | 8 | 0 | | 2 | 8 | 11 | 1 | | 5 | 11 | 14 | 6 | Please let me know if you need any further assistance
2.3. : * Sort the jobs in increasing order of due date. * Schedule each job on the first available machine. Please let me know if you need any further assistance
The maximum lateness is 6.